Baggett Lane Project - Update 3
Published on 11/29/2018
The driveways near the GG side and the front of the units at AA have been scraped away and work continues on the driveway between BB and CC. This may take a day or two longer as they try to get the angle right (the AA/BB building sits on slightly higher ground than the CC/DD building). The goal is to get rainwater to drain either into the center of the aisle or out to the west side of the facility.
The workers are doing what they can to make it so that tenants can still access their units with minimal impact - especially in the late afternoons and evenings as the work is being done during business hours.